Statewide Internet Portal Authority (SIPA)
All proposals to be considered must be received by post or hand delivery by 5:00 pm
Mountain Standard Time, December 13, 2004 and delivered to:
Statewide Internet Portal Authority
C/O: Michael Cooke, SIPA Board Member
State Capitol Annex, Room 404
1375 Sherman Street
Denver, CO 80261
Any proposal that fails to meet the submission deadline will be rejected without opening,
consideration, or evaluation.
Format and Quantities
Prospective contractors are to submit six (6) hard copies not exceeding two hundred
(200) pages. Page format shall be a minimum of 10 point font, double sided (2 pages),
8.5x11 inches. Additionally, one softcopy shall be submitted on a CD in WORD or PDF
format.
4.1 Proposal Content and Organization
This subsection describes minimum information to be included in the proposal. A
prospective contractor is to provide concise, sufficient descriptions of its approach and
solution to the respective requirements of this RFP. Each prospective contractor is
encouraged to submit novel and innovative approaches to demonstrate relevant skills and
experiences. If there are areas where the prospective contractor proposes an alternate
approach, reasoning must be provided as to the benefits of the suggested alternative.
A prospective contract must, with appropriate detail as applicable:
Specify hardware, software, networking, applications, and tools;
Identify the product r function that is licensed from a third party or developed by
the prospective contractor; and
Identify the implementation methodology and on going operations, maintenance,
and support activities.
In the Financial Section of the proposal list the costing information including a
methodology of how the product will be paid for in its entirety or the marginal operating
costs along with the proposed funding source. This section must include how revenue
will be acquired and shared, what costs are to be incurred, and how the costs are to be
shared. FINANCIAL INFORMATION IS NOT TO BE INCLUDED IN OTHER
SECTIONS OF THE PROSPECTIVE CONTRACTOR'S PROPOSAL!
4.1.1 Introduction
Request for Proposal 10/29/2004
6