C. Notwithstanding its role in approving Key Personnel and their replacements, SIPA
shall have no supervisory control over their work, and nothing in this Article shall relieve
the Contractor of any of its obligations under this Contract, or of its responsibility for any
acts or omissions of its personnel.
Article 18: Changes
A. At any time during the period of this Contract, SIPA may request changes in the work,
so long as such changes are within the general scope of the Contract. The Contractor may
also propose changes for consideration by SIPA.
B. A change request from SIPA must be identified as such, must be made or confirmed in
writing, and must be signed by the Responsible Officer identified in Paragraph A of
Article 21 hereof, entitled Responsible Officers. If any other conduct by the responsible
officer or any other representative of SIPA is construed by the Contractor as possibly
constituting a change request or an interpretation of the Contract requirements
inconsistent with the Contractor s understanding of those requirements, the Contractor
shall promptly notify SIPA and request clarification.
C. Within fourteen (14) days after receiving a change request from SIPA, the Contractor
shall submit to SIPA a contract change notice in accordance with the requirements of
Paragraph D of this Article. The Contractor may request a longer period to prepare the
contract change notice, but the Contractor shall make any request for such a longer period
within seven (7) days after the Contractor receives the change request. SIPA shall not
unreasonably withhold its consent to a request for such a longer period, taking into
account the nature of the change request, but SIPA may also take into account the impact
of such an extension on the performance schedule.
D. Whether submitted in response to a change request initiated by SIPA, or initiated by
the Contractor, the contract change notice shall itemize, in a format specified by SIPA,
any impact that the change would have on the technical requirements, price, performance
schedule, or other terms and conditions of this Contract. Where appropriate, the contract
change notice shall also suggest any revised language for the Contract, including any of
its Annexes that would be necessary to implement the change.
E. Any claim by the Contractor for adjustment of the technical requirements, price,
performance schedule, or other terms and conditions of this Contract, attributable to a
change, shall be deemed waived unless asserted in the contract change notice.
F. If the cost of any materials that would be made obsolete as a result of a change is
included in the Contractor s claim for adjustment:
Request for Proposal 10/29/2004