Section E
SECTION E INSPECTION AND ACCEPTANCE
E.1 GENERAL
At a minimum, the following paragraphs shall be applicable to all Task Orders issued
under this Contract, unless otherwise specified by an individual Task Order. Additional
inspection and acceptance requirements may be specified in each Task Order (TO).
E.2 FAR 52.252 2 CONTRACT CLAUSES INCORPORATED BY REFERENCE (FEB
1998)
This Contract incorporates the following Federal Acquisition Regulation (FAR) clauses,
by reference, with the same force and effect as if they were given in full text. The
applicable clauses will be incorporated into the individual Task Orders pursuant to the
Master Contract. Upon request, the Contracting Officer will make their full text available.
Also, the full text of a clause may be accessed electronically on the Internet at
http://www.ARNet.gov/far
.
CLAUSE TITLE DATE
52.246 02 INSPECTION OF SUPPLIES FIXED PRICE
AUG 1996
INSPECTION OF SUPPLIES COST
52.246 03
JAN 2001
REIMBURSEMENT
52.246 04 INSPECTION OF SERVICES FIXED PRICE
AUG 1996
INSPECTION OF SERVICES COST
52.246 05
APR 1984
REIMBURSEMENT
INSPECTION TIME AND MATERIAL AND LABOR
52.246 06
JAN 2001
HOUR
52.246 15 CERTIFICATE OF CONFORMANCE
APR 1984
52.246 16 RESPONSIBILITY FOR SUPPLIES
APR 1984
E.3 CONTRACTOR RESPONSIBILITIES ASSOCIATED WITH INSPECTION,
TESTING AND ACCEPTANCE OF CONTRACTOR PROVIDED PRODUCTS AND
SERVICES
The Contractor is responsible for completion, verification, confirmation and
communication to the Government of all inspections and tests results necessary to
substantiate that the products and services furnished under task orders conform to the
contract and task order requirements. Receipt is not complete and Government testing,
inspection and acceptance need not begin until after the Contractor has fulfilled the
aforementioned responsibilities.
11